MilestoneWith the help of Milestones you can group activities that belong together because they relate to the same intermediate result/deliverable (which is commonly called a milestone). For example, you might want to assign all activities that are related to the first release candidate of a software product to Milestone RC1, or you might want to assign all activities related to passing a chemistry field exam to Milestone Field Exam Chemistry: Anatomy of a Milestone:
You can define as many Milestones as you like and you can assign the same activity to multiple Milestones if required. All the activities assigned to a Milestone are shown in the Grid Activities.
|
||||